Progress continues on the new church. Drywall crews are finishing the chapel, restrooms and entryway. In the main church drywall is finishing up in the cupola. The circular window above the altar was installed. Each of the beams have all been wrapped in wood laminate and stone is being placed around the bottom. In the Narthex and connector building: most rooms are painted, tile is being installed in the restrooms and around the drinking fountain and drop ceiling are hung. Outside the masonry is nearly complete with work wrapping up at the front doors of the Narthex. The shed was torn down.